TENNESSEE — The Tennessee Valley Authority became the first in the U.S. on Tuesday to receive a significant permit to advance development of a small modular reactor. The milestone makes progress for the state of Tennessee to remain a powerhouse of nuclear development throughout the nation.

TVA has been cleared by the U.S. Nuclear Regulatory Commission to move forward with constructing the nation’s first of the GE Vernova Hitachi Nuclear Energy BWRX-300 Advanced Reactor model at the Clinch River Site in Oak Ridge.  

Only one other permit to construct an advanced nuclear reactor has been issued in the country. In March 2026, Wyoming received a permit from the NRC for TerraPower's Natrium Advanced Reactor.

Gov. Bill Lee, Sen. Marsha Blackburn, U.S. Rep. Chuck Fleischmann, U.S. Rep. Tim Burchett and other leaders spoke at the signing ceremony.  

“America’s nuclear renaissance runs through Tennessee, and TVA’s Clinch River site is a big reason why,” Sen. Blackburn said. “This permit brings TVA one step closer to building one of the nation’s first small modular reactors that will power Tennessee homes and businesses with clean, reliable energy, and I applaud TVA and the Nuclear Regulatory Commission for making this moment possible.”

Rep. Fleischmann said the process of getting the permit was expedited due in part to the Trump administration’s support of nuclear advancements. He said the process to receive construction access usually takes several years, but TVA only submitted its application in April 2025. Fleischmann said he helped TVA receive a $400 million federal grant late last year to advance construction of the SMR at Clinch River.  

“Our great state has been ranked No. 1 by outside sources for nuclear [power] in the country,” Flesichmann said. “No other state is near us. Everything is coming together in such a great way, and we are fortunate that it is happening in the state of Tennessee.”

NRC spokesperson David Gasperson said engineers are still in the process of completing site-specific activity at Clinch River, so a specific start date for construction is currently unknown.

“We still have a way to go before you see a lot of construction activity,” Gasperson said. “This is the first big milestone that gives us the confidence that we can actually start nuclear construction. There’s still a lot of work that must go before we do pour nuclear concrete.”

According to a release from TVA, SMRs generate up to 300 megawatts of electricity and are about one-third the size of traditional nuclear units. This smaller design is significant because it can allow models to be built in factories and then shipped to the site. That can reduce construction time, cost and complexity. SMRs require smaller land and water requirements, and components can be added in phases to meet growing energy demand.

TVA provides public power to 10 million people across seven southeastern states: Tennessee, Alabama, Mississippi, Kentucky, Georgia, North Carolina and Virginia.