AUGUSTA — Gov.-elect Hannah Pingree said Tuesday she continues to support a statewide data center moratorium even as a developer in Jay moves forward with plans for a new data center at an old mill site.

“I have not talked to the developers,” she said. “In my campaign we talked about implementing a moratorium until we have rules in place to protect ratepayers, protect the environment and ensure community benefits. That will continue to be my position.”

Pingree also said she has worked with Jay Town Manager Shiloh LaFreniere in the past and is willing to speak with town officials and the developer.

In recent days, JGT2 Redevelopment LLC, which owns the former Androscoggin paper mill, submitted new applications to the Maine Department of Environmental Protection. 

In June, the developers put the project on hold just weeks after Gov. Janet Mills vetoed a data center moratorium so the project could move forward. Mills said she vetoed the legislation because the project enjoyed strong local support.

But on Tuesday in Augusta, her successor and fellow Democrat seemed disinclined to extend the same level of support to the project — at least for now.

During a news conference about her transition team, Pingree said she read about the JGT2 Redevelopment application in the newspaper and is not clear on what might happen with it if a moratorium is put in place while it is pending before DEP.

She also continued to emphasize her position on data centers in general. 

“That being said, heard pretty loudly and clearly from Maine people that the development of data centers in Maine without very strong regulations in place is not something people are interested in,” she said.

Developers hope to turn the old Jay paper mill site into a data center. (Spectrum News file photo)
Developers hope to turn the old Jay paper mill site into a data center. (Spectrum News file photo)

Across Maine, at least 28 municipalities have adopted limits or bans on data centers, according to The Maine Monitor.

Original plans from the developers in Jay call for a small-scale data center that would use the existing electrical grid and tap into less than 1% of the water that had been used by the mill.

It was projected to create nearly 1,000 jobs during construction and lead to 125-150 high paying jobs. 

On Tuesday, engineer Rick Dunton, CEO at Main-Land Development Consultants, told Spectrum News that the Jay project is an opportunity to redevelop the old mill site.

He said the data center is not projected to use more power than the mill and that it will not discharge heated water into the river, which has been an environmental concern with other data center projects.

“A lot of the issues that folks raise with data centers this one generally doesn’t have,” he said.

At the local level, LaFreniere told the Jay selectboard Monday night that Tony McDonald of JGT2 Redevelopment contacted her to say that the project is back on track, although he still has not reached a final agreement with other development partners. 

She said there are tentative plans for an open house at the old mill site on Dec. 10 to give the public a chance to review plans and learn more about the project.

But she also said McDonald is reluctant to say too much at this time.

“He’s a little afraid of crying wolf multiple times and not having what he says actually commence, which has happened a couple of times,” she said.